JXZ0818/2 type gantry moving type double spindle set box of high-speed CNC tube sheet and baffle stack drilling machine is mainly used for boiler industry set header pipe drilling and welding processing of basin shaped hole. Can use twist drill can be used in cold hard alloy cutting tools for high speed drilling processing, no need manual scribing and improve the position precision of the holes and drilling efficiency, realizing the automation of drilling.


Use procedures and precautions:

1.        It is strictly prohibited in high speed CNC header drilling and welding operation (if the welding work is needed in the maintenance and need to disconnect the servo line before the operation).
2.        due to equipment for high speed drilling machine, is strictly prohibited in the unattended operation, operation personnel should remain in operation platform, in order to observe the processing condition. If main, auxiliary processing at the same time, each side of the table are should be operating personnel guard (and equipment operation irrelevant personnel prohibited within the range of move devices to stay to watch).
3.        Operator of the numerical control set box drilling machine is strictly prohibited to wear gloves operating equipment.
4.        To promptly clean up the iron inside the machine, especially the V-shaped slide rails on both sides of the part, if too much, will affect the recycling of cutting fluid, and caused a built-up edge leakage.
5.        Check the level of hydraulic pressure station before boot, if the liquid level is too low, it should be timely to add hydraulic oil, and check whether the equipment has hydraulic oil leakage.
6.        Check the oil level automatic lubricating pump, if too low to replenish.
7.        Check the level of the cooling water tank before boot, if the liquid level is too low, add the cooling water and cutting fluid in time.
8.        When the power is switched on, the power supply is in the order: first, open the cabinet main switch, and then open the system key to control the power supply.
9.        No matter what kind of work, be sure to start the hydraulic unit in the header of a drilling machine side (auxiliary side start hydraulic function).
10.    Hydraulic system, cooling system and chip removal system must be started before the automatic operation of CNC high speed drilling machine.
11.    If the move V support, you need to quickly plug the hydraulic connector loose, move to the target position to connect the corresponding fast plug, the plug is absolutely not allowed to dock errors, can refer to the non move stent. After the completion of the move and rotation test for supporting a shaft is in the a axis rotation rise jointly rotating end common fall. If not, the corresponding plug swap.
12.    If the NC high speed set box drilling machine system, the reference point is lost, the system does not allow automatic operation, the missing reference point of the shaft back to the parameter, the return to the parameters are as follows:
13.    X axis: the move chuck to rear limit position, back to the parameters of the model, "X", the X axis will automatically back to the reference process (back to the reference before can be in manual mode will be the X axis moved to close to the reference point, can be saved back to time reference, because back to the reference is slow)
14.    Z axis: in the return mode, the point on the "Z", the Z axis will automatically complete the return process;
15.    A shaft: because a axis configuration for absolute value encoder, in machine tool debugging after need not return to the reference, if there are special circumstances, chuck lock tight side holes are aligned automatically lock the bolt tightening device, open a shaft parameters will P34210 is set to 1, back to the parameters of the model, "a positive turn, back to participate.

Build a working program, must be under the MDA inspection within the range of the rotation angle of the minimum margins hole whether and the chuck claw conflict. Drilling subroutine in borehole completion retracted position must be higher than the minimum margin hole chuck claw height and preventing chuck rotation of the tool spindle damage.